1. Inspection of Roofs
4. Smoke Alarm Batteries
5. Plaster below skylights
6. Replace light switches
8. Fill up Passage Walls & Touch-up
10. Wall of Forecourt
11. Inspect Drains
16. Repair Concrete
18. Re-pointing round damp course
19. Re-pointing west wall & dampness survey
22. Annual Wall Washing
23. Upper Boards
28. Insulation in Service Duct in the Tunnel
Not reproduced:
3. South door Brass sticks
7. Door Closers & Stoppers
9. Re-surface Forecourt & Manhole covers*
*
12. 1 Fence Post SE of Forecourt
13. Wood Preservative, Fences
15. Drying Area Fence Bar Support Adrift
17. West light switch in tunnel rusting
20. Replacing Wall Tiles*
21. Internal Cleaning Contracts
23. Clean out cubbards under stairs
24. Unblock N Forecourt Drain
25. External Cleaning
26. Hedge Trimming
27. Weeding
Numbers refer to numbers in the 1998 List, those relevant to the current inspection are reproduced with amendments.
The "Backgrounds" given in some items may not necessarilly be sent to potential contractors
The Bills of Works will be used to:
Flat felt roofs are sealed with tar, the purpose of which is to keep the water out of the felt - which otherwise will break up the felt in frost. We have been advised by Chartered Surveyors that the tar should be checked by seeing if the chippings are adherring to the tar, and that the tar is not cracked. The stone chippings are required to keep the roof cool in the sun and prevent fire. It these symptoms occur the treatment is to re-seal the roof with tar, and re-chipping. If this treatment is necessary the life of the roof will be increased somewhat. Our last roof was re-sealed once, and after that only patches showing these symptoms were treated. This proceedure is not generally known in the trade. The Building Research Station has told us that this is the correct proceedure, while generally the design and maintenance of flat roofs is at a very low technical level - causing the lives of such roofs being much less than their potential (Asphalt & built up felt roofing:durability, Digest 144). Annual inspections should also be made of the roof drains, especially after a new roof, to insure they do not get blocked.
Our original roof was a 3-layer felt roof (each layer stuck to gether with tar) with a potential live of 30 years. The present roof is a single layer stuck to a venting sheet (which is not water proof) with a potential life of 10 years (2005). If the above symptoms are found, a decison will have to be made if it will be worth while to undertake the above treatment, with the aim of extending the life of the roof somewhat above 10 years.
There are also 3 small roofs ontop of the service ducts which can deteriorate and need replacing.
The small roof over the ground floor bedrooms has additional problems of water cistern overflows onto it - and one or more of these are liable to keep its surface wet. Vegitation then grows, whoes roots may damage the felt. This small roof had the original 3-layer felt, re-sealed twice, and its design life expired in mid 2000s. It has been leaking, but June 08 correctly replaced, from a partial re-felting done in 1996. However the chippings referred to above have not been applied, together with the surface tar adhering them to the felt - these should have been in the specification. Its also doubtful if the the overlow drains will allow the rainwater to flow off the roof.
After replacement of small bedroom roof:
Apply stone chippings and surface tar
Check evidence of water overflows from Flats' overflows, note which ones
Check condition of piping carrying overflow water off the roof and that rain water
can flow away
Background
It was ageed to purchase re-chargeable batteries. A battery charger is held in Flat 2. The South Block alarms were so fitted, but one went missing in 1994, and the 1st landing battery was changed Autumn 1997, having lasted c 10 years. While these batteries appear to be prone to being stolen, provided they last 3 years they are cheaper than ordinary ones.
Any leak from skylights makes the paint on the plaster come off, then its desireable to check if any leak in the rain, and keep the paint in good condition as a mean of checking on leaks. It is not possible to get an ordinary ladder up the stairs, so it is difficult to reach the skylights
The light swicthes installed in the corridors are not now generally available, and the modern ones do not now fit the recesses in the walls, requiring adapting. Around 1990 the old style switches were still being made, but could only be bought if we placed a bulk order for 6, which was done. One of these remains. . We also have 2 of the old switches - which might be re-furbished by cleaning the contact points. This may be worth attempting, since it may be even more difficult to obtain these switches now - and those removed should be retained not thrown away. Sometimes these switches stick ON - and if they do they are liable to get hot. If residents see a light on continuously they should inform a committee member at once - especially if the switch is getting hot - they are liable to burning the wire insulation, and may start a fire. 3 of the switches now installed in the block are old-style switches, and 3 are new-style switches - 2 of which need replacing.
In the South Block the Ground Floor switch has a press-button which flies out, and needs replacing.
Turn mains off under stairs (key from flats 1 & 9)
Undo the 3 screws and retain them (Screws supplied with new switches
usually not long enough. However some of these original
screws are becoming damaged in their threads and heads,
making them difficult to re-screw, and may cut hands. But
the switches contain screws within them which can
be used - so retain the old switches so these screws
can be used)
Withdraw switch from wall mounting, its wiring will come out also
Undo screws securing wires, and carefully examine wires: if their
insulation is burnt then coat these areas with polystryene
dissolved in acetone (a common glue - flat 2 can supply).
When any such treatment is dry, re-connect the wires to the new
switch as they were in the original one: make sure the
screws are tight
Gently push the switch back into its holder - the wires should
coil up inside.
Re-insert the original screws and tighten (see note above if damaged,
obtained advice from flat 2)
Test the light and see how long it stays on for: these switches
have a screw under the push button - turn it one way and
it stays on longer, the other way less. The light
should stay on long enough to reach the outside (or in
the case of the ground floor to get to the top landing
and open their door) but not much longer. If the timing
is wrong, the three screws need to be undone and the switch
withdrawn again, and the timing altered.
[Where old-style
switches removed, undo the 2 * screws on base of switch, &
examine the contacts. (Do not undo anything else or
switch may explode). Clean the metal contacts with
tissue on a fine screw-driver. Pour some white spirit
into cavity where contacts go when ON, and clean with
tissue on screw-driver. Test with meter (available
flat 2) to see if it gives zero resistance when ON, when
switch may be re-useable on upper floors. If meter
does not give zero resistance, keep the 2 * screws
(when can be used to mount switches on walls).
If there's any fault with the timing plunger its not worth
working on the switch.]
Background
Residents moving furiniture in and out generally cause grooves to be gouged out of the walls of the passages, which need to be filled in again annually. Then they are touched up with paint. A sizeable amount of spare paint should be obtained when walls are painted, so it is availabe to touch up in the following years. This occured when the walls were painted in 1974, and after annual wash, filling and touch-up, did not required further painting until the touch ran out in the late 1990s. The walls painted in the early 2000s, and quite likely the required supply of touch up paint was not laid in - and attempts should be made to acquire this shade.
Background
A vehicle ran into the end of the wall. But the Committee has decided not to re-build it, instead to have a wider entrance. There is substancial re- pointing required along much of this wall, and most of the caps need to be cemented back on again.
All caps need cementing, plus 3 of the long caps between the square caps
--------------------------------------------------------------------------------------------
Drains from time to time get blocked, but when they do they are liable to
result in sewerage coming out of the loos in the ground floor flats as there
is nowhere else for it to go. These can result resulted in insurance claims -
which can result in premium rises. There have been such floods since drains
last inspected.
Thus in the past annual drain inspections were established to prevent
sewerage floods. Greasing manhole covers & bases on replacement is necessary
to prevent them rusting together, especially the main one at the entrance.
Background
The concrete at the door entrances, and through the tunnel & beyond, has
previously become damaged at the surface. This is due to water seeping in,
and shattering the concrete by frost action. The symptons are the surface
breaking up and becoming loose rubble. The choices are to break the whole
concrete up & remove it & re-lay new concrete, or attempt to repair the
surface. It is not practical to attempt the breaking up treatment in the
tunnel since this is the concrete raft on which the block of flats is built.
Infact the concrete entrances are probably part of this raft also as it
extends out the the tarmac.
In the past it has been assumed that the breaking up and re-laying would be
much more expensive than repair. The repair treatment has been sucessfully
done a long time ago on the south concrete entrance. Some years later it
was done at various spots in the tunnel - but at this time we had a drafts-
man in the block who assured us that neat cement should be used (without any
sand which is usually used to make cement). Thus some patches were done with
neat cement, and some done with ordinary cement. It is the neat-cement-only
patches which are now breaking up. The north concrete entrance was repaired
in 1993: but it was also decided to cover it after with factory floor paint
as additional protection to keep out water - this was not done. Some
break-up symptons are in the N concrete entrance (lesser symptoms visible
in S entrance concrete, but this can probably be left for a bit).
The S entrance was repaired with concrete (cement with stones in it), while
N entrance was repaired with cement (i.e. sand and cement mixture). This may
be the reason the S concrete has lasted longer - concete wares better.
Committee decided to repair with fine - moderate concrete, and leave
North entrance for the present, since more must be taken out with concrete
than with cement. Thus tunnel only at present.
Breaking up the concrete is probably wrong due to their being part of the
concrete raft.
Specifications below assume moderate to fine concrete
--------------------------------------------------------------------------------------------------
Background
For some reason, the cement above the damp course tends to turn to powder,
and needs to be regularly inspected and re-ponted.
The Block has suffered from dampness problems:
*some occurring in winter; **No direct cause has ever been found. ###advised that
this is due to drips of water dropping down the cavity in the outside wall,
and splattering on the concrete beams protruding into it and thus splattering
onto the wall at intervals. Action has been to inspect all parts where water
might be getting in, and filling up any potential entrances. This has abated
problem for a while, to return a few years later. Any dampness in the wall
cavity is dangerous from corrosion of the wall ties.
Dampness has occurred in bedrooms of Flats 2,3,8. Residents should periodically
be asked if they have any dampness problems when a full inspection should
be mounted.
The west wall has holes from TV and telephone installations. Some have been
sealed up, but 8 have not been.
The wall tiles below flats' windows are the outer skin of the building, not
decoration. These tiles tend to get broken if ladders are put up against
them (which should be avoided). The tiles hang on nails, but one can only
be replaced by removing the others around it, as other tiles hang over the
nails of others... Only experienced contractor can handle this. The tiles
at the rear (west) of the block are straightforward. But those on the east
of the block are of a shape that cannot generally be obtained. After
many years of search, the contractor Erector offered to replace some
by cutting standard tiles, which was done satisfactorily. We may not want
to use this contractor again, and he may not want to do this job if its
the only one on offer. These tiles are made of cement.
Corridor walls get dirty over a year, especially from moving
furniture in and out of flats. In 1974 they were painted with
paint, which was easilly washed with water and a
little detergent. More stubbon marks may have to have stronger
detergent or other cleaner. A large amoung of paint remaind so
touch-up could continue till 1990s. Re-painting occurred in early
2000s. With high turnover of renters the walls now get dirtier.
---------------------------------------------------------------------------------------------------------
Background
The Upper Boards were originally wood, which like other timber in the Block was
prone to rot. However, use of Dulux Weathershield anti-fungal paint was keeping it
under control with regular inspections. A contractor given the job of doing this persuaded
the committee to change the wood for plastic boards which he claimed would be maintenance
free. He with a sales rep from the manufacturers said there would be a 20 year
insurance backed guarantee. But on my asking to see the insurance policy
the contractor admitted that the guarantee was only for 10 years. Since the economics
was already very marginal at 20 years, I opposed the project, and also showed
that as the felt roof was anchored to these boards they could not be touched
until the roof was replaced. Within a few weeks of the plastic boards being put
on in 1993 some of them blew off on the south side in high winds. No wooden
boards had ever blown off including in the great hurricanes of the late 1980s
which blocked all the roads around with fallen trees. During the 1990s other
plastic boards blew off on the west and north sides. These were eventually put
on again by the contractor. In hot weather the plastic boards could be seen to buckle.
In 1995 I obtained a Chartered Surveyor's report. This found that the wooden boards
could not be replaced separately from the roof which had been destroyed. According
to the manufacturer's specifications the plastic boards should have been nailed
on in two places 60cms apart, but had only been nailed on erratically several
metres apart in one place. The details which join individual plastic boards
together, including at the corners, should also be nailed to the block's
timber members, but none had been. Attempts to enforce the guarantee with
the manufactures obtained a denial that they had been involved or that the contractor
was an authorised installer of theirs. Plans of my committee in 1997 to require the
contractor to put the plastic boards on in accordance with the manufacturer's
specifications or face legal proceedings for damages were abandoned by the
next committee. Further plastic boards were blown off on the west side, which were
replaced by another company on an insurance claim. It is not known if the manufacturer's
specifications were applied.
The NW corner detail is fastened in one place, but no evidence the SW corner
detail is secured or any of the connecting details. Further plastic boards blowing off
is to be expected in the absence of getting these plastic boards put on properly. It is not lawful to make insurance claims as the cause is incorrect installation not
the weather.
The SE corner detail has fallen off, and the NE is slipping down. I have one of these
details.
Minimum action required
28 . BILL OF WORKS: INSULATION IN SERVICE DUCT IN THE TUNNEL
Background
The northern service duct, which carries water and drains, is exposed to frost in the Tunnel.
Thus it was filled during the building by a flake type insulation up to the level
of Flat 9's floor. When in the early years the defective plastic water pipes
were replaced it was necessary to 'drain' the insulation from this duct in the
Tunnel. This was done by taking out some of the bricks at the base to make an
opennng, out of which the insulation was extracted. There is a larger opening
at the top of the duct in the Tunnel where the Duct can be filled with insulation.
More recently it was thought that the insulation had sunk putting water pipes at
risk, and it was topped up with a solid fibre type - up to the level of
Flat 9's floor.
Current problem Summer 2015
The plywood covers of the two openings are deteriorating. Some of the plys of
the lower cover have come away, and the insulation is leaking out.
11. BILL OF WORKS: INSPECT DRAINS
Background
Remove manhole cover for the drains in the forecourt
------------------------------------------------------------------------------
(do not need to remove those by the water drains)
Check that there is no back up of sewerage, & that the yarding eye
by entrance is clear
Arrange for 1 flat in each of the 4 rises to flush a loo
- water should flow rapidly in a spurt about as long as a
loo-flush
Replace manhole covers [generally inspect condition of covers & bases
& grease them - 1998 only needs doing for yarding eye man-
hole by entrance]
- if it comes in a dribble over a long time then it indicates
a blockage is developing in that run.
Report findings
16. BILL OF WORKS: REPAIR CONCRETE
Note: cement & concrete can affect hands - wearing rubber gloves precaution
18. BILL OF WORKS: RE-POINTING ROUND DAMP COURSE
----------------------------------------------------------------------------------------------------
19. BILL OF WORKS: RE-POINTING WEST WALL & DAMPNESS SURVEY
Background
- *condensation running down windows & wetting curtains, especially
flat 2 bedroom
- mould appearing behind furniture placed against walls
- circles of mould appearing along skirting boards of outside walls###
- dampness running down outside wall from above **
West wall: re-point holes where TV wires have been taken through
brickwork. Re-pointing products sold ready to use in gun
form are adequate for small holes
----------------------------------------------------------------------------------------------------
20. BILL OF WORKS: REPLACING WALL TILES
Background
Replace 1 broken tile on north west of building below window flat 11
------------------------------------------------------------------------------------------------------------------
Replace another tile here which is slipping down and likely to be dangerous
Summer 2015
Replace 1 on NE of building
Replace 5 on W of building
22. BILL OF WORKS: ANNUAL WALL WASHING
Background
Wash corridor walls with water and mild detergent.
[*Repairing plaster, and touching up paint is in Bill No. 8]
Remove stubbon marks with stronger detergent, or
other cleaner. Report on marks which cannot be
shifted*
Rince down and dry.
Clean glass of entrance doors in and out (ground floor contract)
23. BILL OF WORKS: UPPER BOARDS
Replace the SE corner detail securing in accordance with manufacturer's specs
-----------------------------------------------------------------------------------------------------------------
Likewise re-fit the NE corner detail
Replace both plywood covers
The upper must be cut to fit the recess
The lower is bigger than the opening, and screwed over it
Check on the height of the insulation, and top up if needed
Screw the new covers back on
They will last longer if painted and in hardboard